We were the main contractor on this build for a local housing developer – Peninsular developments

The house was to be built for the owner of Peninsular developments, so no pressure..

Completed in Spring 2017 – Time to complete, 6 months.

This was a Large Detached new build to our developer’s own spec

Our scope was to :

  • Complete masonry superstructure
  • Install complex timber frame to first floor to support the vaulted roof structure. This all needed to be stick built on site and was a good challenge our carpenters rose to.
  • Install traditional cut roof
  • Install anthracuite foil upvc fascia and soffits
  • Install galvanised gutters
  • Install Siberian larch cladding inc 1 elevation of specially treated NOM COM fire rated cladding
  • Carry out carpentry 1st and 2nd fix
  • Supply and install bespoke oak joinery items